Oxfordshire County Council calls for delay to the DCO submission


Oxfordshire County Council has formally raised serious concerns about Thames Water’s Targeted Consultation on construction access points for the White Horse Reservoir. In its submission, OCC states that the consultation fails to meet three of the four Gunning Principles (the key principles that ensure transparency and fairness in public consultations in the UK), meaning that it cannot be considered a lawful or meaningful consultation.

OCC argues that:

  • The consultation is not at a formative stage, because the Environmental Statement (ES) is already largely drafted and the design “was frozen earlier this year” to allow ES preparation.“It does not appear possible that the scheme will still be in a formative stage by the end of the consultation period…”
  • There is insufficient time for conscientious consideration, with only four weeks between consultation close and Thames Water’s planned November DCO submission.“…there will not be sufficient time for compliance with the fourth [Gunning] principle.”
  • Insufficient information has been provided for consultees to give “intelligent consideration”, – critically – no predicted traffic numbers are presented.“Insufficient information has been provided to give intelligent consideration… No general arrangement drawings nor swept path analysis have been provided…” “If the predicted traffic numbers are not part of this consultation… consultees are substantially constrained…”

OCC also highlights major technical shortcomings, including:

  • Failure to demonstrate maximised use of the rail siding despite national policy requirements.
  • No consideration of internal haul roads – a point that GARD has repeatedly raised.
  • No strategy for reducing construction worker traffic (mobility hubs, shuttles, public transport).
  • Multiple access points proposed on unsafe, narrow or high‑speed roads, with missing safety audits and modelling.

OCC’s conclusion is unequivocal: Thames Water must delay its DCO submission to allow proper consideration of consultation responses and to update the ES accordingly. Without this, OCC states the consultation “cannot comply with the Gunning Principles”.

This is the first time OCC has formally raised the Gunning Principles in writing – a significant escalation that directly challenges the legitimacy of Thames Water’s consultation process.

Its response can be read below:

Past Articles