What is the proposed Abingdon reservoir?

What does Thames Water propose?

Thames Water proposes an above-ground reservoir with walls (‘bunds’) up to 25 metres high, comparable to an eight-storey building. It would hold an extraordinary volume of water—150 billion litres, equivalent to 150 million tonnes in weight (and 1 billion baths), and cover 4.0 square miles (roughly the size of Gatwick Airport). The proposed reservoir is the largest of its kind in Europe — three times bigger than the maximum dimensions of 50 billion litres considered suitable for the site during the public inquiry held in 2010.

Thames Water's Aerial Rendering of Proposed Reservoir

Where will it be?

How will it work?

The proposal would be to pump untreated water from the River Thames to fill a reservoir, with water pumped from Sutton Courtney / Culham, although this is likely to be restricted during high rainfall due to quality concerns. A £1 billion pipeline would then transfer water from the reservoir outside the Thames Valley area to two other water companies, Affinity (15%) and Southern Water (30%). An emergency drain tunnel, currently in early planning stages, would need to be tunnelled under the A34. It would release billions of litres of water into the River Thames at Sutton Courtney / Culham in the event of an emergency.

When would it be built?

What would not be built?

Unlike the nearby Farmoor Reservoir, the proposed Abingdon reservoir is unsuitable for watersports or recreational facilities, with access strictly controlled. Amenities such as walks, trees, and picnic spots are impractical for a reservoir of this size and strategic importance. The reservoir will not effectively aid flood management due to its 25 metre high banks and limited pumping during floods. It cannot fill with rainwater, requiring 70 years to do so, nor would it reduce river pollution, as claimed.

A Timeline of Events

  • 1996

  • 2006 – 2009

  • 2010

    A public inquiry rejects the Abingdon reservoir plans:

  • 2019

  • 2022

  • 2023

    December

  • 2024

    It has since emerged that the Environment Agency, not in favour of the plan, wrote to Thames Water in April 2024 raising 14 issues. Thames Water made changes to the plan in July 2024. These changes and the response were not published until October 2024, after Steve Reed approved it.

    Within this some major alterations were made without any opportunity for public scrutiny. The amendments demonstrate a reduced water deficit after 2050 and further call into question the need for a mega reservoir of this scale and it’s selection as the ‘best value option’.

    Thames Water insist to DEFRA that ‘the level of estimating detail, relative design maturity and significant
    allowances for uncertainty in the SESRO cost estimate give confidence that it is a reliable basis for comparison with other WRMP schemes.’

  • 2025

    GARD and CPRE deliver a petition with over 6600 signatures asking for a public inquiry.

    7 Weeks later Thames Water admitted the costs have escalated from £2.2 to £6.6 Billion

  • 2026

  • 2027 – 2028